高级检索

系杆拱桥吊杆更换的索力转移规律与施工控制研究

Cable Force Transferring Mechanism and Construction Monitoring of Suspender Replacement in Tied Arch Bridge

  • 摘要: 本文以某服役期超过20年的某系杆拱桥为工程背景,针对桥梁吊杆普遍存在的PE护套开裂、钢丝锈蚀等病害问题,探讨了在原位切断旧吊杆并安装新吊杆的施工方案,并利用有限元数值计算和实体桥梁工程施工监测数据,研究了吊杆切除过程索力在临近吊杆的传力规律。为确保结构在换索过程中的受力安全,采用“临时吊杆分级张拉+旧吊杆钢丝分级切割”和“新吊杆分级张拉+临时吊杆分级放张”的两级力系转换方式,实现旧吊杆向新吊杆的平稳索力传递。通过有限元软件ANSYS进行数值分析,同时在实体桥梁关键截面布置振弦式应变计及全站仪监测系统,在旧吊杆上粘贴应变片,实时采集拱肋应力、吊杆索力和桥面位移等关键参数。与实桥监测数据相互验证,得到吊杆索力向相邻两根和四根吊杆传递比例分别为61.0%和92.2%,而旧吊杆索力主要向临时吊杆传递,向临近吊杆索力传递比例变异性较大但是不超过20%,拱肋位移与应力可忽略。施工时,应重点关注桥面位移,为施工监控方案提供技术支撑,从而保障吊杆更换的索力平稳传递与结构受力安全。

     

    Abstract: This article takes a tied arch bridge with a service life of over 20 years as the engineering background. In response to the common problems of PE sheath cracking and steel wire corrosion in bridge suspension rods, the construction plan of cutting the old suspension rod in situ and installing a new one is discussed. Using finite element numerical calculation and actual bridge engineering construction monitoring data, the transmission law of cable force near the suspension rod during the suspension rod cutting process is studied. To ensure the stress safety of the structure during the cable replacement process, a two-stage force system conversion method of "temporary suspension rod graded tensioning+old suspension rod steel wire graded cutting" and "new suspension rod graded tensioning+temporary suspension rod graded releasing" is adopted to achieve smooth cable force transmission from the old suspension rod to the new suspension rod. Numerical analysis was conducted using the finite element software ANSYS, and vibration string strain gauges and total station monitoring systems were installed at key sections of the solid bridge. Strain gauges were attached to the old suspension rods to collect key parameters such as arch rib stress, suspension rod tension, and bridge deck displacement in real-time. Through mutual verification with the monitoring data of the actual bridge, it was found that the proportion of cable force transmitted from the suspension rod to the adjacent two and four suspension rods was 61.0% and 92.2%, respectively. However, the cable force of the old suspension rod was mainly transmitted to the temporary suspension rod, and the proportion of cable force transmitted to the adjacent suspension rod had a large variability but did not exceed 20%. The displacement and stress of the arch rib can be ignored. During construction, special attention should be paid to the displacement of the bridge deck to provide technical support for the construction monitoring plan, thereby ensuring the smooth transmission of cable force during the replacement of suspension rods and the safety of structural stress.

     

/

返回文章
返回