  • 摘要: 近年来,组合式幕墙在高层建筑的应用呈现显著增长趋势,为解决组合式幕墙立面多变、单元板块自重大、收口困难、施工周期长等问题。本文以某高层建筑的玻璃-石材组合式幕墙工程为例,通过优化幕墙单元设计,并采用先吊装玻璃单元板块与石材单元骨架,后挂装石材面板的方案,实现了组合式幕墙的全装配化施工;通过在建筑屋面架设小型专用塔吊作为幕墙吊装设备,确保吊装效率,解决了因建筑立面多变而造成的幕墙吊装不便的难题。同时,对单元式幕墙收口吊装系统、新型单元板夹装机构以及基于BIM的幕墙施工模拟等创新技术进行了总结,并提出了相应的施工要点。结果表明,上述技术能够有效缩短幕墙单元板的安装时间,降低施工成本,具有良好的应用效果,可为其他相关工程提供有益的借鉴。

     

    Abstract: In recent years, the application of combined curtain wall in high-rise buildings has shown a significant growth trend, in order to solve the problems of variable façade, self-importance of unit panels, difficulties in closing, and long construction cycle, etc. of combined curtain wall. In this paper, a high-rise building glass - stone combination of curtain wall project as an example, through the optimization of the curtain wall unit design, and the use of the first lifting glass unit plate and stone unit skeleton, after hanging installed stone panel program, to achieve the combination of the full assembly of the construction of the curtain wall; through the roof of the building to set up a small special cranes as the curtain wall lifting equipment, to ensure that the lifting efficiency, and solved the curtain wall due to the building elevation of the variable and inconvenient problems. The problem of inconvenient lifting is solved due to the change of building elevation. At the same time, innovative technologies such as unit-type curtain wall closure lifting system, new-type unit plate clamping mechanism and BIM-based curtain wall construction simulation are summarized, and corresponding construction points are put forward. The results show that the above technologies can effectively shorten the installation time of the unit plate of curtain wall, reduce the construction cost, have good application effect, and can provide useful reference for other related projects.

     

/

返回文章
返回